Concrete being poured on Riverwalk The construction crew is installing the concrete walkway for the Riverwalk. Today the crews poured and finished 60 +/- yards of concrete. This portion of sidewalk is proposed for a completion date of late September.
Construction Crew Prepares Riverwalk for Concrete Construction crews installed the wood and steel framing on the Riverwalk. The crews are now prepared to pour the concrete walkway.